Cancelled Data Center Projects: Tracker and Statistics (2026)
Every large US data center project that has been withdrawn, denied or dropped since 2024, with planned capacity, announced investment and a source for each.
69
Projects cancelled
Since January 2024, in 26 states
15,910 MW
Planned capacity cancelled
Based on 26 projects that reported capacity
$165 billion
Announced investment cancelled
Based on 32 projects that reported a dollar amount
Cancelled Data Center Project Tracker
| Project | Developer | Location | MW | Investment | Cancelled | Outcome | Reason | Source |
|---|---|---|---|---|---|---|---|---|
| Wildcat Ridge data center campus | Cornell Realty | Archbald, PA | — | $2.1B | Oct 2026 | Denied | Not stated | The Allegheny Front |
| Wisconsin Rapids data center | PNK Group | Wisconsin Rapids, WI | — | — | Oct 2026 | Denied | Not stated | WAOW |
| Concord Township data center | Mission Critical North Iowa | Hancock County, IA | — | — | Oct 2026 | Withdrawn | Not stated | KIOW |
| Brighton data center | Alberta Development Partners | Brighton, CO | — | — | Oct 2026 | Withdrawn | Not stated | Denver7 |
| Henderson data center | Skylar Capital Opportunities | Henderson, NV | 1,000 | $1.5B | Sep 2026 | Withdrawn | Not stated | Government Technology |
| Project Oak | Headwaters Site Development | Coweta County, GA | — | — | Aug 2026 | Denied | Not stated | Times-Herald |
| Ellenwood data center | PCC-DeKalb | DeKalb County, GA | — | — | Aug 2026 | Denied | Not stated | Capital B Atlanta |
| Augusta Township data center | Thor Equities | Augusta Township, MI | — | $1B | Aug 2026 | Denied | Local opposition | WEMU |
| Meridian Technology Park | Eagle Rock Partners | Christian County, IL | 1,000 | $6B | Aug 2026 | Withdrawn | Power or grid | Springfield Business Journal |
| LaOsa data center and energy campus | Vermaland | Pinal County, AZ | 1,000 | — | Aug 2026 | Denied | Local opposition | AZ Family |
| Cetronia Road data center | Air Products | Upper Macungie Township, PA | — | — | Aug 2026 | Denied | Zoning or permitting | WFMZ |
| Stillwater Technology Park | Stillwater Development | Lovejoy, GA | 1,250 | — | Aug 2026 | Withdrawn | Developer strategy | Data Center Dynamics |
| Calvert Cliffs data center campus | Amazon Web Services | Calvert County, MD | 500 | — | Aug 2026 | Withdrawn | Developer strategy | Maryland Matters |
| Convergent Technology Park | Convergent VA | Fauquier County, VA | 240 | $1B | Aug 2026 | Withdrawn | Developer strategy | InsideNoVa |
| Project Iron Spur | The Drox Group | Forsyth County, NC | — | $3B | Jul 2026 | Denied | Local opposition | Public Radio East |
| East Dothan Village data center campus | EdgeConneX | Douglas County, GA | — | — | Jul 2026 | Denied | Zoning or permitting | Douglas County Sentinel |
| Kingsboro AI data center | Energy Storage Solutions | Edgecombe County, NC | 900 | $19.2B | Jul 2026 | Withdrawn | Local opposition | Bisnow |
| Prince William Digital Gateway | QTS and Compass Datacenters | Prince William County, VA | — | — | Jul 2026 | Withdrawn | Zoning or permitting | Data Center Dynamics |
| Tarboro data center | Energy Storage Solutions | Tarboro, NC | 300 | $6.4B | Jul 2026 | Denied | Zoning or permitting | Rocky Mount Telegram |
| Dulles South Innovation Center | Sanders Lane Assemblage I | Prince William County, VA | — | — | Jul 2026 | Denied | Zoning or permitting | Data Center Dynamics |
| Project Washington | Starwood Digital Ventures | New Castle County, DE | 1,200 | — | Jul 2026 | Denied | Zoning or permitting | Spotlight Delaware |
| Holder Industrial Park data center | Deltona Corporation | Citrus County, FL | — | — | Jun 2026 | Withdrawn | Local opposition | Data Center Dynamics |
| Coachella Valley Technology Campus | Stronghold Power Systems | Coachella, CA | 270 | — | Jun 2026 | Deal ended | Local opposition | NBC Palm Springs |
| Gum Springs data center | DC Devco | Clark County, AR | — | — | May 2026 | Deal ended | Not stated | The Arkadelphian |
| Mountain Road Technology Park | Tract | Hanover County, VA | 900 | — | May 2026 | Denied | Zoning or permitting | Richmond BizSense |
| Slavic Village data center | Lakeland Equity Group | Cleveland, OH | 150 | $1.6B | May 2026 | Denied | Not stated | Data Center Dynamics |
| South Annville Township data center | Inch & Company and Eastern Land & Resources | Lebanon County, PA | — | $1.7B | May 2026 | Withdrawn | Not stated | Data Center Dynamics |
| Gardner data center | Beale Infrastructure | Gardner, KS | — | — | May 2026 | Withdrawn | Not stated | KCTV5 |
| Pekin data center | Western Hospitality Partners | Pekin, IL | — | — | May 2026 | Deal ended | Local opposition | Data Center Dynamics |
| Old Ridge Road data center campus | LS Power | Hanover County, VA | 300 | — | May 2026 | Withdrawn | Not stated | Richmond BizSense |
| Nobles County data center | Geronimo Power | Nobles County, MN | 400 | $4B | Apr 2026 | Denied | Local opposition | MPR News |
| Project Atlas | Beale Infrastructure | Coweta, OK | — | — | Mar 2026 | Withdrawn | Not stated | KJRH |
| Apple Valley Technology Park | Oppidan | Apple Valley, MN | 250 | — | Mar 2026 | Denied | Zoning or permitting | Data Center Dynamics |
| Spring Hill data center | Colossus Data Center Advisors | Spring Hill, KS | — | — | Mar 2026 | Withdrawn | Local opposition | Data Center Dynamics |
| New Hill Digital Campus | Natelli Investments | Apex, NC | 250 | — | Mar 2026 | Withdrawn | Local opposition | WUNC |
| Project Spero | TigerDC | Spartanburg County, SC | 100 | $3B | Feb 2026 | Withdrawn | Local opposition | Data Center Dynamics |
| Varina data center campus | Centra Logistics | Henrico County, VA | — | — | Feb 2026 | Denied | Zoning or permitting | Richmond BizSense |
| San Marcos data center | Highlander SM One | San Marcos, TX | — | $1.5B | Feb 2026 | Denied | Local opposition | KUT |
| Montour County data center campus | Talen Energy | Montour County, PA | — | — | Feb 2026 | Denied | Zoning or permitting | Data Center Dynamics |
| Barrington Hills data center | Brennan Investment Group | Barrington Hills, IL | — | $2B | Feb 2026 | Withdrawn | Local opposition | Data Center Dynamics |
| Hunting Hawk Technology Park | HHHunt | Hanover County, VA | 900 | — | Jan 2026 | Withdrawn | Zoning or permitting | Richmond BizSense |
| Clinton County data center | Logix Realty | Clinton County, IN | 300 | $10B | Jan 2026 | Denied | Local opposition | Data Center Dynamics |
| DeForest data center campus | QTS | DeForest, WI | — | $12B | Jan 2026 | Withdrawn | Zoning or permitting | Data Center Dynamics |
| Project Turbo | Project Turbo LLC | Hall County, GA | — | $1.2B | Dec 2025 | Withdrawn | Not stated | Braselton News |
| Breaker Street data center campus | Breaker Street Associates | Jessup, PA | 600 | — | Dec 2025 | Denied | Zoning or permitting | Scranton Times-Tribune |
| Chandler AI data center | Active Infrastructure | Chandler, AZ | — | $2.5B | Dec 2025 | Denied | Local opposition | AZ Family |
| New Carlisle data center campus | New Carlisle 25 Developer | St. Joseph County, IN | — | $12B | Dec 2025 | Denied | Local opposition | 95.3 MNC |
| Howell Township data center | Randee and Stantec | Howell Township, MI | — | $1B | Dec 2025 | Withdrawn | Local opposition | Data Center Dynamics |
| Kalkaska County data center | Rocklocker | Kalkaska County, MI | — | — | Nov 2025 | Withdrawn | Local opposition | Data Center Dynamics |
| Project Cardinal | TAC Data Centers | Great Falls, MT | 500 | $1B | Nov 2025 | Withdrawn | Not stated | Daily Montanan |
| Project Nova | Microsoft | Caledonia, WI | — | — | Oct 2025 | Withdrawn | Local opposition | Data Center Dynamics |
| Project Accelerate | East John Master Development and Matthews DC | Matthews, NC | 600 | — | Oct 2025 | Withdrawn | Local opposition | Queen City Nerve |
| Crooked Creek Technology Park | EagleRock Partners | Jones County, GA | — | $5B | Oct 2025 | Withdrawn | Local opposition | Data Center Dynamics |
| Preble County data center | PRSM | Preble County, OH | — | — | Sep 2025 | Withdrawn | Not stated | Data Center Dynamics |
| Project Flo | Indianapolis, IN | — | $1B | Sep 2025 | Withdrawn | Local opposition | Data Center Dynamics | |
| Blakely data center campus | Michael Mey (applicant) | Blakely, PA | 1,500 | — | Sep 2025 | Withdrawn | Local opposition | Data Center Dynamics |
| Project Aggie | Priority Power Management | College Station, TX | 600 | $1B | Sep 2025 | Denied | Local opposition | Data Center Dynamics |
| Porter County data center campus | QTS | Porter County, IN | — | $2B | Sep 2025 | Withdrawn | Local opposition | Data Center Dynamics |
| Project Cumulus | CRG | St. Charles, MO | — | $1B | Aug 2025 | Withdrawn | Local opposition | KBIA |
| Roxbury Technology Park | Diode Ventures | Charles City County, VA | — | — | Aug 2025 | Withdrawn | Developer strategy | Richmond BizSense |
| Mooresville Technology Park | Tract | Mooresville, NC | — | $30B | Aug 2025 | Withdrawn | Local opposition | Data Center Dynamics |
| Project Lincoln | Western Hospitality Partners | Oldham County, KY | 600 | $6B | Jul 2025 | Withdrawn | Local opposition | WAVE 3 |
| Louisa County third campus | Amazon Web Services | Louisa County, VA | — | — | Jul 2025 | Withdrawn | Local opposition | 29News |
| Buck Creek Township data center campus | Surge Development | Hancock County, IN | — | — | May 2025 | Withdrawn | Local opposition | WRTV |
| Leesburg data center | Prologis | Kosciusko County, IN | — | — | Apr 2025 | Denied | Zoning or permitting | WNDU |
| Pittsylvania County data center campus | Balico | Pittsylvania County, VA | 300 | $8.85B | Apr 2025 | Denied | Local opposition | Cardinal News |
| Harper Road Technology Park | Diode Ventures | Peculiar, MO | — | $1.5B | Oct 2024 | Denied | Local opposition | Data Center Dynamics |
| Chesterton data center campus | Provident Realty Advisors | Chesterton, IN | — | $1.3B | Jun 2024 | Withdrawn | Local opposition | Data Center Dynamics |
| Project Range | Tract | Maricopa County, AZ | — | $14B | May 2024 | Withdrawn | Zoning or permitting | The Real Deal |
69 large data center projects have been cancelled in the US since 2024
The count covers projects of at least 100 MW or $1 billion that a developer withdrew, a local government denied, or that lost their land deal.
The 2026 figure runs through Nov 4, 2026.
Cancelled projects by quarter
| Year | Projects | MW | Investment |
|---|---|---|---|
| 2024 | 3 | — | $16.8B |
| 2025 | 23 | 4,700 | $72.55B |
| 2026 | 43 | 11,210 | $76B |
Cancelled projects add up to at least 15,910 MW of planned capacity
The total is based on the 26 projects that reported capacity. The other 43 did not.
6 of thecancelled projects were planned at 1,000 MW or more.
| Project | Location | Capacity (MW) |
|---|---|---|
| Blakely data center campus | Blakely, PA | 1,500 |
| Stillwater Technology Park | Lovejoy, GA | 1,250 |
| Project Washington | New Castle County, DE | 1,200 |
| Henderson data center | Henderson, NV | 1,000 |
| Meridian Technology Park | Christian County, IL | 1,000 |
| LaOsa data center and energy campus | Pinal County, AZ | 1,000 |
Cancelled projects carried at least $165 billion in announced investment
The total is based on the 32 projects that reported a dollar amount.
6 of the cancelled projects were announced at $10 billion or more.
| Project | Location | Investment |
|---|---|---|
| Mooresville Technology Park | Mooresville, NC | $30B |
| Kingsboro AI data center | Edgecombe County, NC | $19.2B |
| Project Range | Maricopa County, AZ | $14B |
| DeForest data center campus | DeForest, WI | $12B |
| New Carlisle data center campus | St. Joseph County, IN | $12B |
| Clinton County data center | Clinton County, IN | $10B |
Local opposition was cited in 33 of 69 cancellations
The reason shown is the one given in the source for each project.
| Reason | Projects | Share |
|---|---|---|
| Local opposition | 33 | 48% |
| Not stated | 16 | 23% |
| Zoning or permitting | 15 | 22% |
| Developer strategy | 4 | 6% |
| Power or grid | 1 | 1% |
Developers withdrew 39 projects and governments denied 27
| Outcome | Projects | Share |
|---|---|---|
| Withdrawn by the developer | 39 | 57% |
| Denied by a local or state government | 27 | 39% |
| Land or utility deal ended | 3 | 4% |
Virginia has the most cancelled data center projects, with 10
Cancellations are spread across 26 states. 12 stateshave 1 each.
| State | Projects | MW | Investment | Local moratoriums and bans |
|---|---|---|---|---|
| Virginia | 10 | 2,640 | $9.85B | 5 |
| Indiana | 7 | 300 | $26.3B | 35 |
| Georgia | 6 | 1,250 | $6.2B | 69 |
| North Carolina | 6 | 2,050 | $58.6B | 56 |
| Pennsylvania | 6 | 2,100 | $3.8B | 6 |
| Michigan | 3 | — | $2B | 99 |
| Wisconsin | 3 | — | $12B | 46 |
| Illinois | 3 | 1,000 | $8B | 23 |
| Arizona | 3 | 1,000 | $16.5B | 1 |
| Ohio | 2 | 150 | $1.6B | 102 |
| Minnesota | 2 | 650 | $4B | 25 |
| Kansas | 2 | — | — | 22 |
| Missouri | 2 | — | $2.5B | 19 |
| Texas | 2 | 600 | $2.5B | 5 |
| Iowa | 1 | — | — | 38 |
| Florida | 1 | — | — | 36 |
| California | 1 | 270 | — | 34 |
| Kentucky | 1 | 600 | $6B | 29 |
| Colorado | 1 | — | — | 24 |
| Maryland | 1 | 500 | — | 19 |
| South Carolina | 1 | 100 | $3B | 14 |
| Oklahoma | 1 | — | — | 7 |
| Arkansas | 1 | — | — | 5 |
| Nevada | 1 | 1,000 | $1.5B | 5 |
| Delaware | 1 | 1,200 | — | 1 |
| Montana | 1 | 500 | $1B | 1 |
| New Jersey | 0 | — | — | 66 |
| New York | 0 | — | — | 33 |
| Tennessee | 0 | — | — | 30 |
| Washington | 0 | — | — | 21 |
| Nebraska | 0 | — | — | 19 |
| Maine | 0 | — | — | 18 |
| Alabama | 0 | — | — | 15 |
| Utah | 0 | — | — | 8 |
| Massachusetts | 0 | — | — | 6 |
| North Dakota | 0 | — | — | 6 |
| Oregon | 0 | — | — | 6 |
| Connecticut | 0 | — | — | 5 |
| Idaho | 0 | — | — | 4 |
| New Mexico | 0 | — | — | 4 |
| Rhode Island | 0 | — | — | 3 |
| Louisiana | 0 | — | — | 2 |
| Vermont | 0 | — | — | 2 |
| Mississippi | 0 | — | — | 1 |
| New Hampshire | 0 | — | — | 1 |
| South Dakota | 0 | — | — | 1 |
| Alaska | 0 | — | — | 0 |
| Hawaii | 0 | — | — | 0 |
| West Virginia | 0 | — | — | 0 |
| Wyoming | 0 | — | — | 0 |
Local moratoriums and bans since 2022: Data center moratorium tracker
Data Center Watch counted 45 projects blocked or delayed in Q2 2026
| Quarter | Blocked or delayed (Data Center Watch) | Investment blocked or delayed | Cancelled (this tracker) | Investment cancelled | Source |
|---|---|---|---|---|---|
| Q2 2026 | 45 | $68B | 10 | $7.3B | Bisnow |
| Q1 2026 | 75 | $130B | 12 | $28.5B | Data Center Watch |
How We Keep This Page Up to Date
We add a project when a developer withdraws it, a government issues a final denial, or the land deal ends.
Each entry is confirmed by news coverage, public records or a company statement before it’s included.
Update Log
Nov 4, 2026
Removed Indiantown data center after a new application was filed for the site.
Oct 31, 2026
Added Gum Springs data center in Clark County, AR.
Oct 28, 2026
Added 2 projects (Indiantown data center, Project Oak).
Oct 25, 2026
Added Wildcat Ridge data center campus in Archbald, PA.
Oct 22, 2026
Added 2 projects (Wisconsin Rapids data center, Ellenwood data center).
Oct 19, 2026
Added 3 projects (Meridian Technology Park, Augusta Township data center, Project Turbo).
Oct 13, 2026
Added Concord Township data center in Hancock County, IA.
Oct 10, 2026
Added Brighton data center in Brighton, CO. Updated details for Kingsboro AI data center.
Oct 8, 2026
Removed the Green Data Socorro data center, which was paused rather than cancelled. The list now has 59 projects.
Oct 7, 2026
Published the first version with 60 cancelled projects.
How We Track Cancelled Data Center Projects
Cancelled
We consider a data center construction project “cancelled” when a developer withdraws it or the local/state government issues a final denial.
What Is Not Counted
Projects that are paused, delayed, tied up in court or re-filed at the same site are not counted. If a developer moves a project to a different site, the original site is counted. Local bans and pauses are covered in our data center moratorium tracker.
Size
The tracker covers projects of at least 100 MW or at least $1 billion. Where neither figure was published, a project is included if the site is at least 200 acres or the plan is at least 1 million square feet.
Capacity and Investment
MW and dollar figures are announced by the developer or reported at the time. Where a range was given, we use the low end.
Reasons
The reason is the one given in the source. “Local opposition” is used only when the source cites the outcome as resulting from the pushback from residents.
Dates
The date shown is the month the project was withdrawn, denied or dropped. The tracker covers cancellations from January 2024 onward.